MEES and commercial EPCs: the facts in 30 seconds
MEES regulations: what changed on 18 June 2026
For five years, commercial landlords planned around a trajectory of EPC C by 2027 and EPC B by 2030. The 2020 Energy white paper had confirmed EPC B by 2030 as the target, and the 2021 consultation floated an interim C step. On 18 June 2026 the government published an interim response that rewrites that plan. In its own words, the government "is confirming its intention to implement the following":
- "from 2031, it is proposed that all private rented buildings over 1,000 square metres in England and Wales will need to reach a higher standard of energy efficiency of EPC B, where cost effective"
- "the intention is for buildings below 1,000 square metres to continue to be subject to the current minimum standard of EPC E"
- "the previously proposed interim EPC C milestone for 2027 will not be taken forward"
- "existing flexibility mechanisms, including the 7-year payback test and exemptions, will remain in place"
And the catch: "The changes to raise MEES to EPC B for larger buildings will only take effect following the successful passage of secondary legislation through Parliament." Further detail, including how the 1,000 square metre threshold will be measured, is promised in a full government response. For smaller properties the government says there is "no set deadline for going beyond this level".
What that means in plain English: the 2027 cliff edge has gone, the 2030 date has moved to 2031, and the higher bar now only bites on big buildings. But EPC E is still the law today, the penalties are unchanged, and if you own a large building with a lease running past 2031, the clock is ticking on B. Source: GOV.UK interim response, 18 June 2026.
What MEES means for your commercial property: by building size and lease
Find your row. Floor areas are the useful floor area of the building as the rules will define it; the government has said it will set out how the threshold works in its full response.
| Your situation | What the rules say | What to do now |
|---|---|---|
| Any size, rated F or G, currently let | In breach since 1 April 2023 unless a valid exemption is registered | Act now: upgrade to E, or register an exemption if one genuinely applies. Penalties can reach £150,000 |
| Any size, rated F or G, empty and not being marketed | No action needed until you decide to let it again | Plan the works before you market it, so the void doesn't drag on |
| 1,000m² or less, rated E or better | Stays at EPC E under the June 2026 proposals, with no set deadline to go further | You're compliant. Upgrades are now a bills and lettability decision, not a legal one |
| Over 1,000m², rated C to E, lease running past 2031 | Proposed EPC B from 2031, where cost-effective | Get a fresh EPC and its recommendations, cost the route to B, and agree works and access with the tenant early |
| Over 1,000m², lease ending or renewing before 2031 | Proposed EPC B from 2031, where cost-effective | Use the break or renewal: do the disruptive works in the void, and write access and works clauses into the new lease |
| Over 1,000m², already EPC B or A | Already at the proposed standard | Keep the EPC valid when you sell or re-let. An EPC lasts 10 years |
| Lease of 6 months or less, or 99 years or more | Outside MEES (the 6-month rule has conditions) | Check the conditions: a short let with renewal rights, or to a tenant already in occupation for over 12 months, is covered |
| You're the tenant | The MEES duty sits with the landlord | Expect requests for access and consent. Lower bills from upgrades land with you, so negotiate what you share |
Based on GOV.UK's non-domestic MEES landlord guidance (updated 5 May 2026) and the interim response of 18 June 2026. The EPC B proposal is not yet law.
MEES for commercial property today: the EPC E rule
The minimum energy efficiency standards come from the Energy Efficiency (Private Rented Property) (England and Wales) Regulations 2015. For commercial property they have worked in two stages:
- From 1 April 2018: landlords could only grant a new tenancy, or extend or renew one, if the property had at least an EPC E, unless a valid exemption was registered.
- From 1 April 2023: the same rule applies to all privately rented non-domestic property, even where there has been no change of tenancy.
The regulations cover non-domestic rented property that is legally required to have an EPC. GOV.UK's rule of thumb: if the property has been marketed for sale or let, or modified, in the past 10 years, it probably needs one. They don't apply to tenancies with a term certain of 6 months or less (with conditions) or of 99 years or more.
The test is the EPC rating, not your actual bills. A building with low real-world energy use can still fail on its certificate, and a fresh assessment after upgrades is the only way to prove a better rating. Check your current certificate on the GOV.UK EPC register.
MEES penalties: how much a breach can cost
MEES is enforced by Local Weights and Measures Authorities (trading standards). They can serve a compliance notice up to 12 months after a suspected breach, asking for the EPC, the lease, details of works and any energy advice report. Fines are set by regulation 41 of the 2015 regulations:
| Breach | Maximum financial penalty | Plus |
|---|---|---|
| Letting in breach for less than 3 months | The greater of £5,000 or 10% of rateable value, capped at £50,000 | Publication penalty |
| Letting in breach for 3 months or more | The greater of £10,000 or 20% of rateable value, capped at £150,000 | Publication penalty |
| False or misleading information on the Exemptions Register, or ignoring a compliance notice | Up to £5,000 | Publication penalty |
The "publication penalty" means details of the breach go on the public register. Anyone, including your tenants, buyers and lenders, can search it for exempt properties and penalties issued to non-compliant landlords. For an institutional landlord, that can hurt more than the fine.
MEES exemptions and the PRS Exemptions Register
If you can't reach EPC E, you can only keep letting if a valid exemption applies and you have registered it on the Private Rented Sector (PRS) Exemptions Register. Registration is self-certified, and the exemption only applies from the moment you register it. There are six types:
| Exemption | When it applies | Evidence | Lasts |
|---|---|---|---|
| 7-year payback | The recommended measures would not pay for themselves in energy bill savings within 7 years | 3 quotes from qualified installers plus your calculations | 5 years |
| All improvements made | Every relevant improvement has been made (or none can be) and the rating is still below E | The EPC, or a separate report you rely on | 5 years |
| Wall insulation | The only relevant measures are wall insulation and they would damage the fabric or structure | Written opinion of a relevant expert | 5 years |
| Third-party consent | A tenant, superior landlord, lender, freeholder or planning authority refuses consent | Correspondence or the decision notice | 5 years, or until the tenancy ends if tenant consent was the issue |
| Devaluation | The works would cut the property's market value by more than 5% | Report from an independent RICS registered valuer | 5 years |
| New landlord | You've recently become the landlord in certain circumstances | Date and circumstances | 6 months |
- Exemptions don't travel. If you sell a let property, the exemption stops working and the new owner must upgrade or register their own.
- They expire. After 5 years you have to try again to reach E, then register a fresh exemption if you still can't.
- How to register: sign in with One Login, enter the address, choose the exemption and upload the evidence on the GOV.UK PRS Exemptions Register. GOV.UK's assisted digital helpline is 0800 098 7950.
The 7-year payback test is the one that matters most for upgrade planning, and it survives the June 2026 changes. That cuts both ways: it protects you from uneconomic works, but it also means cheap, fast-payback measures such as lighting and controls will almost always be expected.
EPCs for commercial property: when you need one and what it costs to skip it
A commercial EPC rates the building from A (most efficient) to G. Separate from MEES, you must have an EPC for commercial property when you:
- sell or rent out the premises
- finish a building under construction
- change the number of parts used for separate occupation, where that involves providing or extending fixed heating, air conditioning or mechanical ventilation
If you don't make an EPC available to a prospective buyer or tenant, you can be fined £500 to £5,000, based on the building's rateable value. All EPCs are valid for 10 years. You must display the EPC in the building if the useful floor area is over 500 square metres, the building is frequently visited by the public, and an EPC has already been produced for its sale, rental or construction.
Some buildings don't need an EPC at all, including listed or officially protected buildings where the energy requirements would unacceptably alter them, temporary buildings used for 2 years or less, places of worship, low-energy industrial sites, workshops and non-residential agricultural buildings, detached buildings under 50 square metres, and buildings due for demolition with the consents in place.
Your commercial EPC rating is produced by an accredited non-domestic energy assessor, and it comes with recommendations for improving the building. That report is your starting point for any MEES plan, because it is what the 7-year payback test and the "all improvements made" exemption work from.
Which upgrades lift a commercial EPC rating?
Every building is different, so start with your EPC's recommendations and ask the assessor to model a package before you spend anything. These are the measures that come up most often on commercial buildings, and the money that can help pay for them:
| Upgrade | Why it can move the rating | Help with the cost |
|---|---|---|
| LED lighting and lighting controls | Cuts the electricity the assessment assumes for lighting. Usually quick to fit with little disruption, and a cheap measure is more likely to pass the 7-year payback test | Lighting systems are integral features (special-rate plant), which the £1 million Annual Investment Allowance can cover |
| Heating controls and zoning | Better time, temperature and zone control reduces modelled heating use | Space heating systems are integral features (special-rate plant), so the Annual Investment Allowance can cover them |
| Heat pumps | Replacing gas, oil or electric resistance heating with a heat pump can be one of the biggest steps towards B on a heated building | The Boiler Upgrade Scheme isn't just for homes. It pays £7,500 towards an air or ground source heat pump in a small non-domestic building, for systems up to 45kWth (70kWth with more than one heat pump). Until March 2027, a building heated by oil or LPG with no mains gas connection can get an extra £1,500, so £9,000 in total. The scheme now runs to 2030. See commercial heat pumps |
| Solar PV | On-site renewable generation offsets some of the building's modelled electricity use | Solar panels are special-rate plant for tax. The Annual Investment Allowance (£1 million a year) can write off the cost in year one. Above that, companies can claim the 50% first-year allowance. See commercial solar panels |
| Insulation (roof, walls, glazing) | Reduces heat loss, which lowers the heating demand the assessment models | Thermal insulation added to an existing building is special-rate plant for capital allowances |
On business rates: In England, plant and machinery used to generate or store power from on-site renewables (solar included, and batteries where the power stored is mainly or exclusively renewable) is excluded from rateable value until 1 April 2035. Wales (from 1 April 2024) and Scotland (from 1 April 2023) have equivalent exemptions running to 2035. Adding panels to your roof shouldn't raise your rates bill. For every route to funding, from tax allowances to the Boiler Upgrade Scheme and regional loans, see our business energy grants guide.
Landlord or tenant, who pays? The MEES duty is the landlord's, but the bill savings go to whoever pays the energy bills, usually the tenant. Many landlords now agree works, access and cost-sharing in the lease itself. If you're the occupier and want lower bills now, solar and heat pumps can make sense whatever the EPC says. See office solar panels and warehouse solar panels.
Scotland, Wales and Northern Ireland
- Wales: the MEES regulations cover England and Wales, so everything on this page applies, including the June 2026 proposals.
- Scotland: MEES doesn't apply. Under Scotland's own Assessment of Energy Performance of Non-domestic Buildings (Scotland) Regulations 2016, owners selling or letting a non-domestic building over 1,000 square metres must make an action plan for the building available.
- Northern Ireland: MEES doesn't apply. EPCs are still needed when a building is built or marketed for sale or rent, they last 10 years, and district councils enforce the rules.
Your MEES checklist: what to prepare now
- Pull every EPC. Look up each property on the EPC register. Note the rating, the date it expires and the floor area.
- Flag F and G lets first. If any are let without a registered exemption, that's a live breach. Fix those before anything else.
- Sort the estate by size. Separate buildings over 1,000 square metres from smaller ones. The big ones carry the 2031 risk.
- Map lease events against 2031. Breaks, expiries and renewals are your windows for works with the least disruption.
- Get an upgrade model. Ask an assessor to model the route from your current rating to E (or B for large buildings) and cost each step, so you can apply the 7-year payback test honestly.
- Get real quotes for the big items. You'll need 3 quotes anyway to register a 7-year payback exemption. Heat pumps and solar usually need a site survey.
- Line up the money. Check the Annual Investment Allowance, the Boiler Upgrade Scheme and any regional loans before you commit. Talk to your accountant about timing.
When you're ready to price the heavy-lifting measures, we'll pass your enquiry to one suitable commercial installer. You won't be passed round a list or sold on.
Sources checked 28 October 2026
- GOV.UK: Non-domestic MEES, EPC B implementation: interim response (18 Jun 2026)
- GOV.UK: MEES in the non-domestic private rented sector, interim response (18 Jun 2026)
- GOV.UK: Non-domestic MEES landlord guidance (updated 5 May 2026)
- Energy Efficiency (Private Rented Property) Regulations 2015, reg. 41 (penalties)
- Energy Efficiency (Private Rented Property) (England and Wales) Regulations 2015
- GOV.UK: Register a PRS energy standard exemption
- GOV.UK: View the PRS Exemptions Register
- GOV.UK: EPCs for commercial property
- GOV.UK: Find an energy certificate
- Assessment of Energy Performance of Non-domestic Buildings (Scotland) Regulations 2016
- nidirect: Energy Performance Certificates (Northern Ireland)
- GOV.UK: Writing down allowances, rates and pools (special rate: integral features, insulation, solar)
- GOV.UK: Boiler Upgrade Scheme (homes and business buildings)
- Boiler Upgrade Scheme (England and Wales) (Amendment) Regulations 2026: extension to 2030
- HMRC Capital Allowances Manual CA22335: solar panels are special rate
- GOV.UK: full expensing and the 50% first-year allowance
- GOV.UK: Annual Investment Allowance (£1 million)
- Valuation for Rating (Plant and Machinery) (England) (Amendment) Regulations 2022 (SI 2022/405)
- Wales: Plant and Machinery (Amendment) Regulations 2023
- Scotland: Valuation (Plant and Machinery) Amendment Regulations 2023
Great British Energy is an independent guide. We are not affiliated with Great British Energy, the publicly owned energy company (gbe.gov.uk), HM Government, Ofgem or OZEV. Scheme rules and budgets change, so confirm the current position with the scheme administrator before you commit spend. We may receive a fee from the installer we introduce you to.