What is a variable speed drive?
A variable speed drive (VSD) controls how fast an AC motor turns. It rectifies the mains to DC, then builds a new AC supply at whatever frequency and voltage the motor needs, so the motor turns only as fast as the demand requires.
An ordinary induction motor wired straight to the mains runs at one speed, set by the 50 Hz supply and the number of poles. That suits a conveyor that always moves at the same rate. It doesn't suit a fan, a pump or an air handling unit that only needs full output on the hottest afternoon or the busiest shift.
Without a drive, sites control those machines the wasteful way: a damper closes in the duct, a valve throttles the pipe, or water is bypassed back round the loop. The motor keeps running at full speed and pushes against the restriction. A drive does the same job electronically.
You'll see the same kit called a variable frequency drive (VFD), an inverter drive, an AC drive or an adjustable speed drive. They are the same thing. Some pumps and fans now arrive with the drive built on top of the motor, which the Carbon Trust calls an integrated motor drive.
Motors matter to your bill more than most people think. The Carbon Trust's motors and drives guide quotes World Energy Council estimates that, globally, motor-driven systems account for 70% of electricity use in industry. On a factory, a plant room or a large air-conditioned building, motors are usually the biggest single block of electricity you can control.
The cube law: why a small speed cut saves so much
Centrifugal fans and pumps follow what engineers call the affinity laws. Flow rises in line with speed, pressure with speed squared, and power with speed cubed. The Carbon Trust's wording is that on these loads "the power varies with the change in speed cubed", so "a 20% speed reduction will result in up to approximately a 50% power saving".
| Motor speed | Flow (in line with speed) | Shaft power (speed cubed) | Power saved, before drive losses |
|---|---|---|---|
| 100% | 100% | 100% | 0% |
| 90% | 90% | 72.9% | 27.1% |
| 80% | 80% | 51.2% | 48.8% |
| 70% | 70% | 34.3% | 65.7% |
| 60% | 60% | 21.6% | 78.4% |
| 50% | 50% | 12.5% | 87.5% |
Two things keep the real figure below the table. The drive loses some energy as heat, which the Carbon Trust puts at typically 5%. And many pump systems have to lift water to a fixed height or hold a minimum pressure, so the speed can only come down so far before flow stops. That's why the Carbon Trust says "up to". Fans moving air round a building, and pumps circulating water round a closed heating or chilled water loop, get closest to the cube law. Pumps lifting water up a building or into a tank get less.
The quick test: if a fan or pump has a damper, valve or bypass that is partly closed for much of the year, it is a candidate for a drive. If the motor runs at full output all the time with nothing choked back, it isn't.
Work out the saving on your own motor
You don't need a model or a salesperson's percentage. You need four numbers: the motor's rated kW from its nameplate, the hours it runs a year, how hard it works, and your electricity unit price from your bill. The Carbon Trust's running cost formula is:
Annual running cost = (motor kW ÷ motor efficiency) × loading × hours × price per kWh
The guide suggests 0.75 as a default loading if you don't know it. Better still, have the motor's current logged for a week, which any decent installer will do before quoting.
Worked example 1: an air handling unit fan on dampers
An office supply fan has a 15 kW motor at about 92% efficiency, works at 75% load and runs 4,000 hours a year (weekdays, long hours). We use 25p per kWh as an example. Use the unit rate on your own bill, because the sum moves in direct proportion to it.
- Electrical input now: 15 ÷ 0.92 × 0.75 = 12.2 kW
- Energy now: 12.2 × 4,000 = 48,900 kWh a year, about £12,200
- Logging shows dampers hold the airflow at about 80% for most of the year. Slowing the fan to 80% instead: 0.8³ = 51.2% of the power
- Allow typically 5% for drive losses: 51.2% ÷ 0.95 = about 54% of today's input
- Energy with a drive: about 26,400 kWh a year, a saving of roughly 22,500 kWh, about £5,600 a year
That's a best case for a fan sitting on the cube law. If the dampers are only partly closed for half the year, halve the saving. If your unit rate is 20p rather than 25p, take a fifth off.
Worked example 2: the same motor on a conveyor
Put that 15 kW motor on a conveyor, which is a constant torque load. The Carbon Trust says power on these loads "is directly proportional to speed", so slowing it 20% saves about 20%, less the drive's own losses. That's roughly 16% net (0.8 ÷ 0.95 = 84% of today's input), about 7,700 kWh and £1,900 a year at the same hours and price, and only if the line genuinely can run slower. If the conveyor has to run at full speed, a drive saves nothing on energy and adds its own losses. You'd buy it for soft starting or process control, not for the bill.
Worked example 3: payback
Payback is the installed price divided by the annual saving. If a drive for the fan in example 1 is quoted at £3,000 installed, payback is £3,000 ÷ £5,600, about six and a half months. If it is quoted at £6,000 because the panel needs rebuilding, it's about 13 months. The Carbon Trust's own guide says drives "can payback in less than two years in some applications". Ask every installer to show this sum, with their logged figures, before you sign.
Where variable speed drives pay, and where they don't
| Load type | Examples | How power changes with speed | Verdict |
|---|---|---|---|
| Variable torque | Centrifugal fans, AHUs, extract fans, cooling tower fans, heating and chilled water pumps | With speed cubed | Best case. Up to about 50% saved for a 20% speed cut |
| Constant torque | Conveyors, screw and reciprocating compressors, crushers, mixers | In line with speed | Worth it where output genuinely varies. A 50% speed cut saves about 50% |
| Constant power | Machine tools, centre winders | Power stays about the same | Rarely any energy saving |
| Always at full speed | A fan or pump with nothing throttled, a motor already matched to its duty | No speed cut possible | No saving. The drive adds its own losses |
The plant that most often pays well in commercial buildings is the air handling unit, the heating and chilled water pumps and the extract fans, especially where the building's controls can tell the drive what's actually needed. That's where a drive and a building management system work together: the BMS reads a pressure or temperature sensor and turns the fan down, rather than leaving it at the commissioning speed for ten years. The same goes for the heating pumps on a commercial boiler plant room.
In factories, look at process cooling pumps, dust and fume extraction, and compressed air. A variable speed compressor suits a site whose air demand swings. Where demand steps between fixed levels, the Carbon Trust notes that running two machines in parallel under a sequencer may suit better than a drive.
When a variable speed drive is not worth buying
Drives are sold hard, and not every motor needs one. Hold off if:
- The motor already runs at the output it needs, all the time. No damper, no throttled valve, no bypass. There's nothing to slow down, and the drive's own losses (typically 5%) make the bill slightly worse.
- It runs few hours. A 4 kW pump that runs 500 hours a year can't save enough to repay a drive, even on the cube law. Run the formula above and look at the pounds, not the percentage.
- The load is constant power. Machine tools and centre winders rarely save anything from a speed cut.
- The motor is badly oversized. The Carbon Trust says a motor should be loaded at 50% of its rating or higher for efficient running. A right-sized motor, or trimming a pump impeller, can beat a drive on a fixed duty and costs less.
- The problem is the system, not the speed. Slack belts, blocked filters and undersized pipework waste energy whatever the motor speed. Properly maintained belts run at 94% to 98% efficiency, according to the guide, and fixing those first changes what the drive needs to do.
- The motor is old and failing. Rewinding costs efficiency: the Carbon Trust's worked example assumes a motor loses 2% efficiency in one rewind. Replacing it with an IE3 or IE4 motor and fitting the drive at the same time is often the better spend.
Harmonics and power factor: what a drive does to your supply
A drive draws current from the mains in pulses as it charges its DC stage. Those pulses add harmonics, currents at multiples of 50 Hz, to your supply. One or two small drives won't matter. A plant room full of them, or a few large ones, can heat cables and transformers, trip sensitive kit and upset a capacitor bank.
- Power factor correction. If your site has an existing capacitor bank, adding drives can make it resonate with the new harmonics and fail early. Our power factor correction guide explains why sites with drives usually need a detuned bank, and why a power factor survey should log harmonics as well.
- Don't put capacitors on a drive's output. The old trick of fitting a capacitor to each motor doesn't work on a motor fed from a drive. Correction belongs at the main board, sized with the drives in.
- Line reactors and filters. Many drives come with a DC choke or can take an input line reactor. On larger installations, an active harmonic filter or a low-harmonic drive may be specified.
- The network operator's view. Harmonic limits for connecting equipment like this to the GB networks are set out in the Energy Networks Association's Engineering Recommendation G5/5. A large drive project, especially one alongside factory solar panels or a battery, may need the installer to show harmonic data to your network operator.
Drives usually improve the displacement power factor the supply sees from that motor, though their harmonics pull true power factor down. The net effect on an existing reactive power charge varies, so if you add a lot of drives, recheck what correction you still need before you buy more kVAr.
Motor efficiency classes and the ecodesign rules in Great Britain
In England, Scotland and Wales the rules for new motors and drives are in the Ecodesign for Energy-Related Products and Energy Information Regulations 2021 (SI 2021/745), which replaced the EU regulation for Great Britain. They apply to what manufacturers place on the market, not to motors already running on your site. You don't have to replace a working motor, but anything new you buy should meet them.
| Product | Rated output | Minimum level | From |
|---|---|---|---|
| Three-phase motors | 0.75 kW to 1,000 kW | IE3 | 1 July 2021 |
| Three-phase motors | 0.12 kW to below 0.75 kW | IE2 | 1 July 2021 |
| Three-phase motors, 2, 4 or 6 poles | 75 kW to 200 kW | IE4 | 1 July 2023 |
| Ex eb increased safety motors | 0.12 kW to 1,000 kW | IE2 | 1 July 2023 |
| Single-phase motors | 0.12 kW and above | IE2 | 1 July 2023 |
| Variable speed drives (3 phase input, 100 V to 1,000 V AC) | For motors 0.12 kW to 1,000 kW | Power losses no higher than IE2 | 1 July 2021 |
Note that "IE2" means different things for motors and drives. For a motor it is an efficiency class. For a drive it is a ceiling on the drive's own power losses. The motor rules cover 2, 4, 6 and 8 pole induction motors rated 50 V to 1,000 V for continuous duty. The regulations don't make a drive compulsory on any motor. SI 2021/745 extends to England, Wales and Scotland only, so in Northern Ireland check which rules apply with your supplier.
What this means when you buy: if a quote replaces an old motor, it should be at least IE3, and from 75 kW to 200 kW at least IE4. If your motors predate these rules, ask the installer to price motor and drive together. An old IE1 motor that has been rewound is the classic candidate.
Tax relief, loans and grants for variable speed drives
Annual Investment Allowance. GOV.UK says "The AIA amount is £1 million" and that you can claim it "on most plant and machinery". For most businesses, that writes a drive project off against profits in the year you buy it.
Full expensing and first-year allowances. Companies paying Corporation Tax can claim full expensing (100%) on new and unused main rate plant, or a 50% first-year allowance on special rate plant. Since 1 January 2026 there is also a 40% first-year allowance for new main rate plant that unincorporated businesses and leasing can use. In its 29 October 2026 Budget document, the government proposed raising that to 50% for expenditure from 1 January 2027, with legislation to come in the Finance Bill.
Main rate or special rate? HMRC doesn't name drives. Its list of integral features (CA22320), which are special rate, includes "an electrical system" and "a powered system of ventilation, air cooling or air purification". A drive fitted to an air handling unit may follow the ventilation system it belongs to. A drive fitted to a production machine is more likely to follow that machine. Within the £1 million AIA the difference rarely matters. Above it, ask your accountant.
Scotland. The Business Energy Scotland SME Loan lists "Variable speed drives" and "Energy efficient motors and controls" among the measures eligible for an interest-free loan and up to 75% cashback. Loans run from £1,000 to £130,000, and cashback for energy efficiency is capped at £20,000, subject to funds.
Wales. The Development Bank of Wales Green Business Loan Scheme lists "Key equipment improvement" and "monitoring & controls" and says its list "isn't exhaustive". It doesn't name drives, so ask before you apply. The Development Bank of Wales also offers a grant of up to 50% of a detailed energy audit, to a maximum of £10,000. See our Wales business energy guide.
England and Northern Ireland. There's no national grant for drives. Some councils fund measures from an energy survey: see council business energy grants, our wider business energy grants guide and the Northern Ireland guide. Public sector bodies should look at Salix funding. Every kWh a drive saves also comes off your Climate Change Levy, a flat charge per unit of electricity.
How a drive survey works
- Motor list. Every motor above a few kW, with its nameplate kW, what it drives, how it's controlled now and its run hours. Plant rooms often have more motors than anyone remembers.
- Logging. A clamp-on logger on the biggest candidates for a week or more shows how hard each one really works, and when.
- Shortlist and sums. The installer ranks motors by pounds saved, using the formula above, and flags the ones where a new IE3 or IE4 motor should go in at the same time.
- Specification. Drive rating, enclosure, harmonic measures, the control signal (a BMS sensor, a pressure transducer or a fixed set speed) and any bypass for the drive failing.
- Proof. After installation, the same logger, or your half-hourly meter data, shows the drop. In a public building, the saving also feeds the next Display Energy Certificate, which is based on metered energy use.
Drives are usually one line in a wider survey. A business energy audit ranks them alongside LED lighting, voltage optimisation and controls, and large companies can raise them in their ESOS assessment and describe them in the energy efficiency section of their SECR report. Our business energy saving guide covers the no-cost measures to do first.
Sources checked 20 November 2026
- Carbon Trust: Motors and drives technology overview guide (CTV048v3, May 2018)
- Ecodesign for Energy-Related Products and Energy Information Regulations 2021 (SI 2021/745), Schedule 16: motors and variable speed drives
- SI 2021/745, regulation 33: which motors and drives are covered
- GOV.UK: Annual Investment Allowance (£1 million)
- GOV.UK: full expensing and the 50% first-year allowance
- GOV.UK: 40% first-year allowance (from 1 January 2026)
- GOV.UK (29 Oct 2026): proposed 50% main rate first-year allowance from 1 January 2027
- HMRC Capital Allowances Manual CA22320: integral features
- Business Energy Scotland: SME Loan
- Development Bank of Wales: Green Business Loan Scheme
- ENA Engineering Recommendation G5/5: harmonic planning levels and connecting non-linear equipment
Great British Energy is an independent guide. We are not affiliated with Great British Energy, the publicly owned energy company (gbe.gov.uk), HM Government, Ofgem or OZEV. Scheme rules and budgets change, so confirm the current position with the scheme administrator before you commit spend. We may receive a fee from the installer we introduce you to.